Skip to content

TotalEnergies E&P UK Upstream Operational Information

As required under Regulation (EU) No 1227/2011 on wholesale energy market integrity and transparency (REMIT), this page provides information on the planned maintenance and unplanned unavailability of infrastructure operated by Total E&P UK Limited.

Whilst every effort is made to ensure that the information is given in good faith and to the best of our knowledge and belief at the time of posting, no warranty is given as to the accuracy or completeness of that information.

Notification of Planned Unavailability

ASEP

Revision

Date Published

Event Date

Expected Duration

Loss of
Volume 
(mcm/d)

Comments

NSMP - SF 0 30/06/2022  19:10:31 01/08/2022 ~6 Days 8 Elgin Franklin planned maintenance, export rates will start ramping down on the 31st July. Restart and ramp up of export planned to start during gas day 6th August.
NSMP - SF 0 30/06/2022  18:58:03 15/08/2022 ~7 Days 3 Planned maintenance at Alwyn. Expectation is there will be a three day ramp up to normal export levels once the maintenance is complete.
NSMP - SF 1 14/06/2022  10:20:01 23/06/2022 2 Days 4.5 Laggan Tormore pigging resulting in zero export for approximately 2 days. POSTPONED.
NSMP - SF 0 09/06/2022  20:27:53 23/06/2022 ~2 Days 4.5 Laggan Tormore pigging resulting in zero export for approximately 2 days. Dates may still change.
NSMP - SF 4 29/05/2022  07:57:43 29/05/2022 1 Day 4.2 Planned maintenance at Laggan Tormore. Delay in restarting, issues with compressor. Restart not expected until Sunday 29th.
NSMP - SF 3 27/05/2022  17:06:34 27/05/2022 3 Day 4.2 Planned maintenance at Laggan Tormore. Delay in restarting, issues with compressor. Restart not expected until Sunday 29th.
NSMP - SF 2 27/05/2022  05:53:54 27/05/2022 1 Day 4.2 Planned maintenance at Laggan Tormore. Delay in restarting. Some gas may be delivered during gas day 27th May.
NSMP - SF 1 24/05/2022  08:19:42 24/05/2022 2 Day 4.2 Planned maintenance at Laggan Tormore. Some gas may be delivered during gas day 26th May.
NSMP - SF 0 08/05/2022  11:36:19 21/05/2022 ~7 Day 4.2 Planned maintenance at Laggan Tormore. A ramp up in rates should be expected at end of maintenance.
Teeside CATS 6 24/04/2022  22:25:45 24/04/2022 1 Day 0 Pitstop for ESD Testing - ramp up nearly complete, production at pre-shutdown levels.
Teeside CATS 5 24/04/2022  13:47:28 24/04/2022 1 Day 6.8 Pitstop for ESD Testing - ahead of planned and restarted. Ramp up to full rates by tomorrow's gas-day 25th April.
Teeside CATS 4 24/04/2022  07:07:08 24/04/2022 1 Day 6.8 Pitstop for ESD Testing - ahead of planned and restart is imminent.
Teeside CATS 3 23/04/2022  23:22:10 23/04/2022 2 Days 11.8 Pitstop for ESD Testing - shut down as planned but withdrawing a quantity from stock.
Teeside CATS 2 23/04/2022  20:35:47 23/04/2022 2 Days 12.5 Pitstop for ESD Testing - shut down as planned but withdrawing a quantity from stock.
Teeside CATS 1 23/04/2022  18:25:39 23/04/2022 2 Days 14.2 Pitstop for ESD Testing - shut down as planned but withdrawing a quantity from stock.
Teeside CATS 0 17/03/2022  13:10:35 23/04/2022 ~2 Days 15.5 Pitstop for ESD Testing.
             

Notification of Unplanned Unavailability

ASEP

Revision

Date Published

Event Date

Expected Duration

Loss of
Volume 
(mcm/d)

Comments

Bacton SEAL 3 24/07/2022  22:22:45 25/07/2022 2 Days 3 Elgin Franklin ramp up is ongoing. Full rates expected by gas-day 25th July.
Bacton SEAL 2 24/07/2022  08:26:24 25/07/2022 2 Days 7 Elgin Franklin export has restarted and flows from Bacton SEAL will commence at 10:00hrs. Slow ramp up to full rates throughout the gas-day.
Bacton SEAL 1 24/07/2022  08:22:26 25/07/2022 2 Days 7 Elgin Franklin export has restarted and flows from Bacton SEAL will commence at 10:00hrs. Slow ramp up to full rates throughout the gas-day.
Bacton SEAL 0 23/07/2022  06:18:10 24/07/2022 ~1 Day 10 Egin Franklin export has stopped. Investigation into cause ongoing, restart date unknown. Delivery from Bacton SEAL is forecast to stop from 9am this morning. Approx. 3.0 MCM/D of gas being delivered to the Bacton Perenco terminal by Elgin Franklin will stop at 9am also.
Bacton SEAL 3 18/07/2022  22:31:12 19/07/2022 1 Day 0 Elgin Franklin export has restarted and currently ramping up to full rates. It is anticipated that flows from Bacton SEAL will commence from 23:00hrs onwards.
Bacton SEAL 2 18/07/2022  21:41:38 19/07/2022 1 Day 8 Elgin Franklin export has restarted and currently ramping up to full rates. It is anticipated that flows from Bacton SEAL will commence overnight.
Bacton SEAL 1 18/07/2022  12:15:29 18/07/2022 1 Day 8 Egin Franklin export has stopped due to a trip on the booster compressor. Export is expected to restart later this gas day. Delivery from Bacton SEAL is forecast to stop from 1300 today. Approx. 3.0 MCM/D of gas being delivered to the Bacton Perenco terminal by Elgin Franklin will stop at 1300 also. Restart time currently unknown.
Bacton SEAL 0 18/07/2022  08:13:35 18/07/2022 ~1 Day 8 Egin Franklin export has stopped due to a trip on the booster compressor. Export is expected to restart later this gas day. Delivery from Bacton SEAL is forecast to stop from 11am this morning. Approx. 3.0 MCM/D of gas being delivered to the Bacton Perenco terminal by Elgin Franklin will stop at 11am also. Restart time currently unknown.
Bacton SEAL 3 08/07/2022  11:31:59 08/07/2022 1 Day 11 Gas Delivery at Bacton SEAL for Elgin Franklin is due to start at 1300 hours at 3.0 MCM/D. Rates at Bacton SEAL will increase to previous levels by early evening. Elgin Franklin delivery into Bacton Perenco is forecast to start from 1400 - Elgin Franklin rates at Bacton Pereco expected to be around 2.9 MCM/D later this afternoon.
Bacton SEAL 2 08/07/2022  06:01:36 08/07/2022 1 Day 11 Gas export has restarted from Elgin Franklin, another message will be published when gas export from Bacton SEAL is expected to restart.
Bacton SEAL 1 07/07/2022  23:43:02 08/07/2022 1 Day 11 Compressor trip on Elgin Franklin, Compressor has been restarted. It's not certain when gas export will be restarted. Currently export from SEAL terminal is now forecast to stop at 0100.
Bacton SEAL 0 07/07/2022  23:37:08 08/07/2022 ~1 Day 11 Compressor trip on Elgin Franklin, Compressor has been restarted. It's not certain when gas export will be restarted. Currently export from SEAL terminal is forecast to stop at 0300.
Bacton SEAL 0 06/07/2022  11:31:47 08/07/2022 ~2 Days 0 Blending gas that was being nominated to the Bacton Perenco terminal will be nominated at the SEAL terminal from midday 06-Jul-2022. Increasing the delivery at the Bacton SEAL terminal from current levels of 8.75 MCM/D by ~2.4 MCM/D.
Bacton SEAL 4 24/06/2022  14:16:54 25/06/2022 1 Day 0 Back to normal production levels.
Bacton SEAL 3 24/06/2022  07:56:04 25/06/2022 1 Day 0 Issues offshore resolved, flows at SEAL will commence at 10:00hrs with a slow ramp up during the course of this gas-day.
Bacton SEAL 2 22/06/2022  18:30:55 25/06/2022 3 Day 8 Due to ongoing issues offshore, Elgin Franklin gas export is now forecast for gas-day 24th June. Once gas export is achieved, pipeline stocks will need to be replenished before flows at SEAL commence.
Bacton SEAL 1 21/06/2022  21:54:51 23/06/2022 1 Day 8 Restart of Elgin Franklin gas export is not anticipated until gas-day 22nd June, flows at SEAL will commence after pipeline stocks are replenished.
Bacton SEAL 0 21/06/2022  10:40:53 22/06/2022 ~1 Day 8 Elgin Franklin has tripped, investigation ongoing. Rates at SEAL forecast to go to zero at 1300hrs, restart time currently unknown.
NSMP - SF 4 06/06/2022  06:09:19 06/06/2022 1 Day 2.1 Reduced production from Laggan Tormore for compressor maintenance.
NSMP - SF 3 05/06/2022  16:21:31 05/06/2022 2 Day 2.4 Reduced production from Laggan Tormore for compressor maintenance.
NSMP - SF 2 04/06/2022  23:46:53 05/06/2022 2 Day 2.1 Reduced production from Laggan Tormore for compressor maintenance.
NSMP - SF 1 03/06/2022  20:38:14 03/06/2022 3 Day 2.4 Reduced production from Laggan Tormore for compressor maintenance.
NSMP - SF 0 03/06/2022  06:53:24 03/06/2022 ~3 Day 3.4 Reduced production from Laggan Tormore for compressor maintenance.
Teeside CATS 1 15/04/2022  15:01:08 15/04/2022 1 Day 5.0 Culzean trip - restart process ongoing.
Teeside CATS 0 15/04/2022  14:03:15 15/04/2022 ~1 Day 2.8 Culzean trip - restart process ongoing.
Bacton SEAL 2 02/04/2022  21:21:56 03/04/2022 2 Days 0 Ramp up quicker than expected, full rates from 22:00hrs onwards.
Bacton SEAL 1 02/04/2022  13:16:44 03/04/2022 2 Days 5.0 Elgin Franklin has restarted. Delivery at SEAL terminal is forecast to begin from 15:00hrs. It is anticipated that there will be a slow ramp up for the rest of the gas-day with full rates tomorrow.
Bacton SEAL 0 01/04/2022  20:13:50 02/04/2022 ~1 Day 7.0 Trip on Elgin Franklin. Delivery at SEAL terminal is forecast to reduce over the next few hours and stop from 2300hrs. Restart is currently unknown as investigations ongoing.
Teeside CATS 4 23/03/2022  11:54:16 24/03/2022 1 Day 1.2 Culzean almost back to normal levels.
Teeside CATS 3 23/03/2022  06:25:35 24/03/2022 1 Day 7.0 Culzean ramp up slower than forecasted.
Teeside CATS 2 23/03/2022  05:23:02 24/03/2022 1 Day 1.2 Culzean has restarted and export rates increasing. Available Capacity of 160 GWh/D is the forecast for gas day 23-Jun-2022.
Teeside CATS 1 23/03/2022  05:13:31 24/03/2022 1 Day 1.2 Culzean has restarted and export rates increasing. Available Capacity of 160 GWh/D is the forecast for gas day 23-Jun-2022.
Teeside CATS 0 22/03/2022  22:55:04 23/03/2022 ~1 Day 7.3 Culzean trip, it's hoped that export is restarted before the end of this gas day.
Bacton SEAL 4 12/03/2022  06:27:33 12/03/2022 2 Days 0 Elgin Franklin export has restarted, Technical capacity not expected until gas day 12th March.
Bacton SEAL 3 12/03/2022  00:22:32 12/03/2022 2 Days 4 Elgin Franklin export has restarted, Technical capacity not expected until gas day 12th March.
Bacton SEAL 2 11/03/2022  16:35:56 10/03/2022 2 Days 8 Elgin Franklin export has restarted, SEAL stock being built. Delivery at Bacton SEAL will resume early evening. Technical capacity not expected until gas day 12th March.
Bacton SEAL 1 10/03/2022  16:19:13 10/03/2022 1 Day 8 Elgin Franklin restart processes underway, at this time it’s not clear when gas delivery will restart at Bacton SEAL. Once restarted it will take up to 24 hours to return to previous rates.
Bacton SEAL 0 10/03/2022  16:19:13 10/03/2022 ~1 Day 8 Trip on Elgin Franklin. Delivery at SEAL terminal is forecast to reduce over the next few hours and stop from 2000 Export is not due to restart until tomorrow with stock requiring to be rebuilt, restart of delivery at SEAL is estimated.
             

Historic Information

2021 Upstream operational information

2020 Upstream operational information

2019 Upstream operational information

2018 Upstream operational information

2017 Upstream operational information

2016 Upstream operational information